Right of Way: Why Nigerian Fibre Costs More Than It Should (2026)

Last updated: November 2026 · Reading time: about 12 minutes

A fibre optic cable crew laying duct in an open trench beside a Nigerian road, illustrating how state right-of-way charges drive up the cost of fibre deployment in 2026
Quick answer Because ₦145 per linear metre is a headline, not a price. Eleven states waive right-of-way entirely and 17 cap it at the national rate, but others charge ₦1,500 to ₦6,600 per metre — and even compliant states add application fees up to ₦700,000. ALTON says right-of-way can account for 50–60% of the cost of deploying a kilometre of fibre in some states. The NCC attributed an 85% jump in operator operating costs to ₦5.85 trillion in 2024 partly to RoW fees. The real problem is not the rate — it is that each of 36 states runs its own permit regime, and states that waive the fee often replace it with development, environmental and capital-placement levies. A zero-RoW state with a ₦700,000 application fee is not a cheap state. The BRIDGE project's 90,000km at roughly $2 billion only works if the landed cost per kilometre falls, and that is a state policy question, not an engineering one.

The ₦145 myth

In 2020 the National Economic Council directed states to adopt a uniform right-of-way charge of ₦145 per linear metre to accelerate broadband rollout. Before harmonisation, fees ranged from ₦4,000 to ₦8,000 per metre depending on the state. On paper, a 96% reduction.

On the ground, the reduction has been partial, uneven, and in several states entirely nominal. The reason is structural: right-of-way is a state-level approval, not a federal one. The NCC can negotiate, publish guidance and name and shame, but it cannot set a state's permit fees. Each of the 36 states and the FCT runs its own process, with its own rate, its own application fee, and its own set of ancillary levies.

The result is a national policy that produces wildly different landed costs per kilometre, depending on which state a fibre route happens to cross. That is the single most important thing to understand about Nigerian broadband economics: the cost of connecting two points is a function of the number of state boundaries between them.

What states actually charge

Nigerian right-of-way charges by state against the 145 naira national benchmark A bar chart comparing selected state right-of-way charges per linear metre against the 145 naira benchmark. Ogun charges the highest at 6,600 naira, followed by Kano at 2,754, Delta at 2,706, Rivers at 2,256, Akwa Ibom at 2,000 and Osun at 1,500. Eleven states charge zero. A side panel lists application fees ranging from 10,000 to 700,000 naira. Right of Way: The ₦145 Benchmark vs What States Charge PER LINEAR METRE · 2026 Selected state RoW charges (₦ per metre) National benchmark: ₦145/m 6,600 Ogun 2,754 Kano 2,706 Delta 2,256 Rivers 2,000 Akwa Ibom 1,500 Osun 0 11 states Application fees on top Even where the RoW rate is compliant Ekiti: ₦700,000 (compliant rate) Taraba: ₦350,000 Cross River: ₦250,000 Adamawa: ₦100,000 (zero RoW) Oyo: ₦50,000 Yobe: ₦25,000 Gombe: ₦10,000 PLUS OTHER LEVIES Development levy per linear metre, education, environment, effluent, capital deployment fees ALTON: RoW can be 50–60% of the cost of deploying one kilometre of fibre in some states. GSMA: non-compliance with the harmonised rate pushes deployment costs up by as much as 70%. Full compliance would cut deployment costs by roughly 15%, not transform them.

Here is the current spread, from NCC ease-of-doing-business data and industry reporting.

State RoW charge per linear metre Status against the ₦145 benchmark
Ogun ₦6,600 Highest listed charge — roughly 45× the national rate
Kano ₦2,754 Not aligned
Delta ₦2,706 Not aligned
Rivers ₦2,256 Not aligned
Akwa Ibom ₦2,000 Not aligned
Osun ₦1,500 Charges a rate above the cap despite being listed among reform states
17 states ₦145 Compliant with the National Economic Council cap
11 states ₦0 Waived entirely — Anambra, Katsina, Kebbi, Nasarawa, Osun, Plateau, Adamawa, Bauchi, Enugu, Benue, Zamfara
State rates and lists change frequently, and different sources count the waiver states differently. Some reporting counts 13 or 15 states as having scrapped charges, depending on whether partial waivers and conditional waivers are included. Verify against the most recent NCC ease-of-doing-business data before relying on any specific figure. The table illustrates the spread, not a definitive register.

The spread matters because fibre routes are linear. A 200km route from Lagos toward Ibadan crosses state boundaries, and each boundary can reset the rate. An operator planning a national backbone is not comparing ₦145 to ₦6,600 on average — it is choosing whether to route around states, delay, or absorb the cost. All three outcomes slow deployment.

The application-fee backdoor

The more subtle problem is that the headline rate is only one line in the cost stack.

State Application fee Note
Ekiti ₦700,000 Adopted the ₦145 rate but imposes the highest identified application fee
Taraba ₦350,000 On top of the applicable rate
Cross River ₦250,000 Also applies the ₦145 rate
Adamawa ₦100,000 Has removed the RoW charge entirely, but still charges per application
Oyo ₦50,000 Added to the ₦145 rate
Yobe ₦25,000 On top of the standard fee
Gombe ₦10,000 Among the lower-cost states

An application fee is charged per application, not per metre. On a long route the per-kilometre effect of a ₦700,000 fee is modest. On the short metro links that connect a data centre to a backbone, or a business park to a ring, it is substantial — and those are precisely the links that determine whether a fibre network serves customers or just passes through.

ALTON's chairman has been explicit that some states replace formal RoW charges with other levies, making the apparent concession less meaningful. His list of the charges operators encounter includes development levies per linear metre, educational levies, environmental levies, effluent discharge fees and capital deployment fees. A state that announces a zero RoW rate and then charges a development levy per metre has not reduced the cost of laying fibre; it has renamed it.

“Zero RoW” does not mean zero cost

The eleven waiver states are a genuine improvement, and the NCC has linked them to faster fibre expansion — Kaduna and Niger are cited as among the most advanced users of the policy. The $1 billion in operator investment commitments that followed the reforms is a real signal.

But three caveats matter for anyone reading a headline about waiver states.

  • Application fees survive the waiver. Adamawa has removed the RoW charge and still requires ₦100,000 per application. The fee is smaller, not zero.
  • Ancillary levies survive the waiver. The development, environmental and capital-placement levies listed by ALTON are separate from the RoW charge and are not automatically abolished when the rate goes to zero.
  • Approval time is a cost. The NCC has repeatedly cited delays in approvals and multiple permitting requirements as discouraging investment. A zero-fee permit that takes nine months costs more in delayed revenue than a ₦145 permit that takes three weeks, because the capital is committed either way.
The comparison that matters: a state charging ₦145 per metre with a ₦50,000 application fee and a three-week approval can be cheaper than a state charging zero with a ₦700,000 application fee and a six-month approval. Rate headlines do not capture approval time, and approval time is the variable operators complain about most.

What this does to deployment economics

Three independent estimates of the cost effect, all pointing the same direction.

Source Finding
ALTON (Gbenga Adebayo, 2026) Right-of-way can account for 50–60% of the total cost of deploying one kilometre of fibre in some states
GSMA Non-compliance with the harmonised rate pushes deployment costs up by up to 70%; full compliance would cut costs by about 15%
NCC (2024 industry data) Operator operating costs rose 85% to ₦5.85 trillion, attributed primarily to high RoW fees alongside inflation, FX pressure and energy costs

Note the tension between the ALTON and GSMA figures. If RoW were 50–60% of deployment cost in a typical state, full compliance with ₦145 would do far more than cut costs by 15%. The reconciliation is that ALTON's 50–60% applies to some states — the high-charge ones — while GSMA's 15% is a national average across compliant and non-compliant states. Both are correct about different populations. This is exactly the kind of figure that gets flattened into a single misleading headline.

The macro context makes the cost question urgent. Broadband penetration stood at 48.81% in August 2025 and about 49.3% by September 2025, against a National Broadband Plan target of 70% that the country will not meet. The government's BRIDGE project aims to roll out 90,000km of fibre at roughly $2 billion. At that budget the implied cost is around $22,000 per kilometre. Every state that adds ₦2,000–₦6,600 per metre — or ₦2–6.6 million per kilometre — is adding a material fraction of that budget to the route.

The second cost layer: cuts and vandalism

Right-of-way is the cost of laying fibre. There is a second cost of keeping it working, and it is large enough to change the investment case on its own.

Between January and August 2025, Nigeria recorded 19,384 fibre cut incidents, 3,241 cases of equipment theft, and over 19,000 denials of access to telecom sites. Each cut is a repair crew, a service interruption and, in some cases, a regulatory reporting obligation. Road construction is a frequent cause, which is why coordination between state works ministries and fibre operators matters as much as the permit fee.

This is where the policy conversation often stops too early. Reducing the RoW fee lowers the cost of the first kilometre. Protecting the fibre from cuts lowers the cost of every subsequent year of operation. A state that charges zero but has uncoordinated roadworks and no protection regime for telecom infrastructure is not a low-cost state over a five-year horizon.

What would actually fix it

Five measures, in order of impact.

  1. Legislate, do not just negotiate. The National Economic Council directive is a resolution, not a statute. ALTON has called for legislation making right-of-way access free, particularly in rural and low-return areas. A law with a penalty for non-compliance would do more than another round of engagement, because a state that ignores a resolution risks nothing.
  2. Standardise the whole permit, not just the rate. Publish a single schedule covering the RoW charge, the application fee, the ancillary levies, the approval timeline and the appeal route. Operators can plan around a known cost; they cannot plan around a cost that varies by ministry.
  3. Set an approval clock. A published maximum approval period, with deemed approval if the clock expires, converts an unbounded delay into a bounded one. This is the intervention that operators would value most and that costs states the least.
  4. Coordinate roadworks with fibre routes. Ducting installed during road construction costs a fraction of trenching afterwards. Requiring ducts in new road projects would eliminate a large share of the cut incidents and the re-excavation cost simultaneously.
  5. Use the USPF strategically. The Universal Service Provision Fund exists to subsidise deployment in areas where commercial returns do not justify private capital. ALTON has argued it should be deployed more aggressively in exactly the rural locations where RoW charges make the economics impossible.

The National Digital Economy and E-Government Bill, reported to have reached third reading and expected to pass before the end of 2026, is the most likely vehicle for the first two measures. Whether it includes an enforceable RoW provision is the thing to watch.

Frequently asked questions

What is right of way in Nigerian telecoms?

Right of way is the fee a state or local authority charges for permission to lay fibre-optic cable along public roads and land. The National Economic Council directed states in 2020 to adopt a uniform ₦145 per linear metre charge, down from fees that had ranged from ₦4,000 to ₦8,000 per metre depending on the state.

How much do states actually charge for right of way?

Nigeria right of way: the 145 naira benchmark versus state charges up to 6,600 naira per metre Left panel shows a road cross-section with a fibre duct laid in a trench and a measuring tape along the surface. Right panel shows three price tags: the 145 naira national benchmark, 6,600 naira per metre in Ogun, and a 700,000 naira application fee in Ekiti. A bottom band notes that right of way can be 50 to 60 percent of fibre deployment cost in some states. Right of Way: The ₦145 Benchmark vs What States Charge Why Nigerian fibre costs more than it should — per linear metre, 2026 NIGERIA One kilometre of fibre, laid PER METRE, EVERY METRE PUBLIC ROAD — STATE RIGHT OF WAY TRENCH DUCT fibre cut fibre cut 19,384 fibre cut incidents and 19,000+ denials of site access were recorded between January and August 2025. Every metre of this trench is chargeable, by each state it crosses. The permit is issued by the state, not by the NCC. What the same metre costs NATIONAL BENCHMARK · 17 STATES ₦145 / m OGUN · HIGHEST LISTED ₦6,600 / m 45× benchmark EKITI · APPLICATION FEE, ON TOP ₦700,000 per application 11 states waive RoW entirely — but application fees, development levies and environmental fees remain. A ₦145 rate with a 3-week approval can be cheaper than a ₦0 rate with a 6-month approval. ALTON: right of way can be 50–60% of the cost of deploying one kilometre of fibre in some states. GSMA: non-compliance pushes deployment costs up by up to 70%; full compliance would cut them by about 15%. dedontech.blogspot.com

It varies enormously. Eleven states have waived the charge entirely and 17 cap it at ₦145 per metre. But Ogun charges ₦6,600 per metre, Kano ₦2,754, Delta ₦2,706, Rivers ₦2,256, Akwa Ibom ₦2,000 and Osun ₦1,500. On top of the rate, application fees run from ₦10,000 to ₦700,000.

Why is Ogun's right-of-way charge so high?

Ogun has consistently been listed as the highest-charging state, at ₦6,600 per linear metre in current NCC ease-of-doing-business data — roughly 45 times the national benchmark. Earlier operator-compiled figures put it higher still. The state has not aligned with the National Economic Council cap.

If a state waives right of way, is fibre deployment free?

No. Application fees survive the waiver — Adamawa has removed the RoW charge and still requires ₦100,000 per application. Ancillary levies including development levies per linear metre, educational levies, environmental levies and capital deployment fees are separate from the RoW charge. Approval delays are also a cost, because committed capital earns nothing while a permit is pending.

How much of fibre deployment cost is right of way?

ALTON estimates right-of-way can account for 50–60% of the total cost of deploying one kilometre of fibre in some states. The GSMA estimates that non-compliance with the harmonised rate pushes deployment costs up by up to 70%, and that full compliance would cut costs by roughly 15%. The two figures describe different populations — high-charge states versus a national average.

Why does this matter for broadband in Nigeria?

Broadband penetration was about 49.3% in September 2025 against a 70% national target. The BRIDGE project aims to lay 90,000km of fibre at roughly $2 billion, which implies about $22,000 per kilometre. Every state charging ₦2,000–₦6,600 per metre is adding ₦2–6.6 million per kilometre to a route, which is a material share of that budget.

What would fix the right-of-way problem?

Legislation rather than a resolution, so non-compliant states face a consequence. A standardised permit covering the rate, the application fee, ancillary levies and the approval timeline. A published maximum approval period with deemed approval on expiry. Ducting requirements in new road projects to reduce fibre cuts. And more aggressive use of the Universal Service Provision Fund for rural routes where commercial returns do not justify private capital.

Disclaimer: This article is general information and analysis about Nigerian telecom infrastructure policy as of November 2026. It is not legal or investment advice. State charges, waiver lists and application fees change frequently and are reported inconsistently across sources — verify against the most recent NCC ease-of-doing-business data and state regulator publications before relying on any specific figure. Some figures cited are operator-compiled rather than official, and are identified as such where they appear.
About the author
Amedu Danjuma is a technology specialist and analyst based in Nigeria, evaluating business software since 2016. He writes about legal technology, insurance technology and fintech for Dedon Tech, focusing on pricing structures, feature gaps and the difference between what a product does and what its marketing says it does. Product and compliance claims are checked against primary sources, and the editorial policy explains that process.

Related reading on Dedon Tech: MTN Nigeria vs Airtel Africa: where telecom capex actually turns into ARPU · does mobile money actually lift ARPU? · the case for accelerated tech infrastructure investment in Nigeria and Africa · full site map

Data sources: Nigerian Communications Commission ease-of-doing-business data on right-of-way charges; ALTON statements at the 2026 Nigerian Economic Summit; GSMA estimates on harmonisation and deployment cost; NCC 2024 industry operating cost data; BusinessDay, Vanguard and Punch reporting on state RoW charges and application fees, 2026; National Broadband Plan 2020–2025 progress reporting.